47 days to Stadtbahn Glattal
Last Monday (16th October), trial running on phase one of Glattalbahn commenced. An official press demonstration run took place yesterday (23rd). Unfortunately, I have until now been unable to capture any such moments on film (or SD card). However, I have uploaded some scenes (taken on 18th and 19th of this month) of the completed line, including impressions of the high quality to which the stops are finished. The second part of the gallery has pictures of phase two (the airport line), construction of which is now making rapid progress. The alignment has been cleared in many places and excavation of the Lindbergh to Bhf. Glattbrugg tunnel has begun. View the gallery. Search news archive for Stadtbahn Glattal.